Client: Lindum Group
Project Duration: 2 Weeks
Completion Date: July 2017

Mobile Office Relocation – East Lindsey District Council, Skegness

FMS was asked by the Lindum Group if we could arrange for the removal and relocation of a 40ft mobile office from within an industrial unit, this included the disconnection of water, foul water and the electrical & data supplies.

The ramp system was to be removed and rebuilt.

The mobile office had to be removed from the building on skates as the Haib lorry was unable to gain access into the building and lift the mobile unit because of the roof height.

The mobile building was successfully relocated. This was carried out at dawn on a summers morning to avoid causing traffic issues along the main Skegness seafront during the summer holiday period.

The mobile office was to be relocated to a new site to be used by East Lindsey District Council.